S-20LS Fukushima Yamatsuri
Total Module Output |
1,327.36kW |
Number of Installed Modules |
7,808 |
Total Output |
1,220kW |
FIT Price |
36JPY/kWh |
End of FIT |
November 6, 2036 |
Interconnection |
Tohoku Electric Power |
Annual Energy Production on First Operating Year (Expected) |
1,558.99MWh |
Availability Factor on First Operating Year (expected) |
13.41% |
Operator |
Takara Leben |
EPC |
NIKADEN, Sata Construction |
Manufacture of Module |
Solar Frontier |
Supplier of Power Conditioner |
DELTA ELECTRONICS |
O&M Provider |
ORIX Facilities |
Land Area |
27,026㎡ |
Land Rights |
Superficies |
Type of Module |
CIS |
|
|
|
|
|
|
|
|
Total Module Output |
1,327.36kW |
Number of Installed Modules |
7,808 |
Total Output |
1,220kW |
FIT Price |
36JPY/kWh |
End of FIT |
November 6, 2036 |
Interconnection |
Tohoku Electric Power |
Annual Energy Production on First Operating Year (expected) |
1,558.99MWh |
Availability Factor on First Operating Year (expected) |
13.41% |
Operator |
Takara Leben |
EPC |
NIKADEN, Sata Construction |
Solar Frontier |
Solar Frontier |
Supplier of Power Conditioner |
DELTA ELECTRONICS |
O&M Provider |
ORIX Facilities |
Land Area |
27,026㎡ |
Land Rights |
Superficies |
Type of Module |
CIS |