S-01LS Shioya


Total Module Output 2,987.25kW
Number of Installed Modules 11,949
Total Output 1,990.00kW
FIT Price 40JPY/kWh
End of FIT July 30, 2033
Interconnection TEPCO
Annual Energy Production on First Operating Year (expected) 3,254.193MWh
Availability Factor on First Operating Year (expected) 12.44%
Operator Takara Leben
EPC SHARP
Manufacture of Module SHARP
Supplier of Power Conditioner Fuji Electric
O&M Provider Energy O&M.Inc
Land Area 36,727㎡
Land Rights Ownership
Type of Module Monocrystalline Silicon
Total Module Output 2,987.25kW Number of Installed Modules 11,949 Total Output 1,990.00kW FIT Price 40JPY/kWh
End of FIT July 30, 2033 Interconnection TEPCO Annual Energy Production on First Operating Year (expected) 3,254.193MWh Availability Factor on First Operating Year (expected) 12.44%
Operator Takara Leben EPC SHARP Manufacture of Module SHARP パワコン供給者 富士電機株式会社
O&M Provider TOYO BLDG MAINTENANCE Land Area 36,727㎡ Land Rights Ownership Type of Module Monocrystalline Silicon