S-29LS Chiba Sammu East/West
Total Module Output | (East) 2,584.00kW (West) 2,475.20kW |
Number of Installed Modules | (East) 15,200 (West) 14,560 |
Total Output | (East) 1,990.00kW (West) 1,990.00kW |
FIT Price | 36JPY/kWh |
End of FIT | March 29, 2037 |
Interconnection | TEPCO Power Grid |
Annual Energy Production on First Operating Year (Expected) | (East) 3,132.28MWh (West) 3,007.94MWh |
Availability Factor on First Operating Year (expected) | (East) 13.84% (West) 13.87% |
Operator | Takara Leben |
EPC | Toshiba Plant Systems & Services Corporation |
Panel Manufacturer | Solar Frontier K.K |
PCS Manufacturer | Toshiba Mitsubishi-Electric Industrial Systems Corporation |
O&M Provider | Toyo Bldg.Maintenance Co.,Ltd. |
Land Area | 138,762㎡ |
Land Rights | Ownership |
Type of Module | CIS |
Total Module Output | (East) 2,584.00kW (West) 2,475.20kW |
Number of Installed Modules | (East) 15,200 (West) 14,560 |
Total Output | (East) 1,990.00kW (West) 1,990.00kW |
FIT Price | 36JPY/kWh |
End of FIT | March 29, 2037 | Interconnection | TEPCO Power Grid | Annual Energy Production on First Operating Year (expected) | (East) 3,132.28MWh (West) 3,007.94MWh |
Availability Factor on First Operating Year (expected) | >(East) 13.84% (West) 13.87% |
Operator | Takara Leben | EPC | Toshiba Plant Systems & Services Corporation | Panel Manufacturer | Solar Frontier K.K | Supplier of Power Conditioner | Toshiba Mitsubishi-Electric Industrial Systems Corporation |
O&M Provider | Toyo Bldg.Maintenance Co.,Ltd. | Land Area | 138,762㎡ | Land Rights | Ownership | Type of Module | CIS |