(S-05) LS Kirishima Kokubu

As of May 20, 2020
9th Fiscal Period (ending May 31, 2020)

May 24, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
05:29 to 16:04 (JST) 0.02% 0.50%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

May 19, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
05:54 to 16:02 (JST) 0.02% 0.48%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

May 13, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
05:32 to 16:02 (JST) 0.02% 0.46%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

May 8, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
05:38 to 16:03 (JST) 0.02% 0.44%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

May 6, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:12 to 16:02 (JST) 0.02% 0.42%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

May 4, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:13 to 16:02 (JST) 0.02% 0.40%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

April 29, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
05:45 to 16:07 (JST) 0.02% 0.38%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

April 27, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
07:21 to 16:02 (JST) 0.02% 0.36%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

April 22, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
05:58 to 16:03 (JST) 0.02% 0.34%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

April 16, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
07:07 to 16:03 (JST) 0.02% 0.32%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

April 9, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:08 to 16:10 (JST) 0.02% 0.30%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

April 6, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:10 to 16:02 (JST) 0.02% 0.28%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

April 4, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:15 to 16:36 (JST) 0.02% 0.26%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

March 29, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:30 to 16:02 (JST) 0.02% 0.24%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

March 20, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:35 to 16:02 (JST) 0.02% 0.22%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

March 15, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:41 to 16:04 (JST) 0.02% 0.20%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

March 14, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:47 to 16:03 (JST) 0.02% 0.17%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

March 12, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:43 to 17:19 (JST) 0.03% 0.15%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

March 11, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:42 to 16:03 (JST) 0.02% 0.13%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

March 8, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
06:46 to 16:02 (JST) 0.02% 0.11%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

February 24, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
07:03 to 16:16 (JST) 0.02% 0.08%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

February 23, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
07:01 to 16:03 (JST) 0.02% 0.07%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

February 20, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
07:16 to 16:04 (JST) 0.02% 0.05%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

January 5, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
07:33 to 16:04 (JST) 0.02% 0.03%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020

January 1, 2020

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 9th fiscal period ending May 31, 2020
This curtailment Total curtailments for the entire fiscal period
07:33 to 16:05 (JST) 0.02% 0.02%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 9th fiscal period ending May 31, 2020