(S-05) LS Kirishima Kokubu

As of November 18, 2019
8th Fiscal Period (ended November 30, 2019)

November 15, 2019

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 8th fiscal period ended November 30, 2019
This curtailment Total curtailments for the entire fiscal period
7:18 to 16:11 (JST) 0.02% 0.05%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 8th fiscal period ended November 30, 2019

November 6, 2019

Affected Period Ratio of loss of power generation to total estimated power generation of the entire portfolio for the 8th fiscal period ended November 30, 2019
This curtailment Total curtailments for the entire fiscal period
7:52 to 16:15 (JST) 0.02% 0.02%
  • The ratio is rounded off to third decimal place
  • This curtailment has no impact on the forecasted performance for the 8th fiscal period ended November 30, 2019